Date
|
Task
|
Completed By
|
Comments
| |
June 2013 - November 2013
|
Assorted Research and Planning Tasks
|
- Martin Stewart
- Grace Cuthbertson
|
All Tasks Completed
| |
9th December 2013
|
Shoot Day 1
|
- Grace Cuthbertson
- Martin Stewart
|
Actors Present
| |
10th December 2013
|
Shoot Day 2
|
- Martin Stewart
- Grace Cuthbertson
|
Actors Present
| |
11th December 2013
|
Shoot Day 3
|
- Grace Cuthbertson
- Martin Stewart
|
Actors Present
| |
12th December 2013
|
Editing Day
|
- Martin Stewart
- Grace Cuthbertson
| ||
13th December 2013
(Rough Cut Deadline Day 6pm)
|
Final Editing Day
|
- Grace Cuthbertson
- Martin Stewart
| ||
13th - 15th December 2013
|
Evaluation of Rough Edit by Peers
|
N/A
|
Through use of youtube and social media
| |
16th - 21st December 2013
|
- Re-Shoot any unsatisfactory footage
- Iron out any mistakes spotted by peers
|
- Martin Stewart
- Grace Cuthbertson
|
Actors Present if any shots need to be re-done
| |
22nd December 2013 - 10th January 2014
(Final Edit Deadline Day)
|
- Complete all editing and shooting for submission of final music video
|
- Grace Cuthbertson
- Martin Stewart
|
The production schedule was one of the most important tasks as it clearly outlines what we will be doing on what days over the course of the project. It allows us to plan things such as work around our shooting schedule and also around our most important editing days. To see our detailed schedule of what we will be doing on the days of the shoot see here: http://martingracea2media.blogspot.co.uk/2013/11/call-sheet.html